BESS Hold Point Testing: Clearing Energisation Roadblocks

Know what BESS hold point testing needs before energisation: the program, test logs and reports to have ready. A practical guide from BESST Engineering.

Your battery can be built, wired and ready to run, and still wait at a hold point until the testing is finished and reported. Here is how BESS hold point testing works in the National Electricity Market (NEM) and where your evidence needs to be in order.

What Does BESS Hold Point Testing Involve Before You Can Energise?

A hold point is a stage in your commissioning program where testing has to be completed and reported before the project moves on. AEMO’s published guidance puts three pieces of paperwork around that process:

  • Commissioning program: you submit it to the network service provider (NSP) and AEMO. The guidance asks for it at least three months ahead for a transmission connection and one month ahead for a distribution connection.
  • Test logs: these go to the NSP and AEMO at the end of each day of testing.
  • Hold point report: you submit one to the NSP and AEMO when each hold point is completed, using AEMO’s template for commissioning under NER 5.8.

AEMO recommends agreeing on the scope early. Check your connection agreement and NSP requirements for each hold point, and update your evidence list if testing methods or staging change.

Where Evidence Tends to Fall Short at a Hold Point

In BESS hold point testing, a report is only as strong as the records behind it. When you review your own, look for these gaps:

  • Untraceable results: a test result you cannot link to a requirement in your performance standards or connection agreement.
  • Settings that have drifted: controller, inverter or protection settings on site that differ from the ones your studies assumed.
  • Open protection questions: a protection philosophy that is still unresolved against the NSP’s requirements.
  • Thin records: logs without raw data, calibration records or consistent timestamps.
  • Late changes: equipment or firmware changes that nobody has assessed against the approved design.

Closing a gap before you submit is usually simpler than answering a request for information afterwards. Give every open item an owner, so you always know who is chasing what.

How Independent Review Fits Around Your Hold Point Evidence

We review the evidence behind your hold points. We do not run your tests, design your plant, build models or self-certify anything. We check whether your records trace back to your requirements, list the open defects and structure the evidence so the gaps are visible. Our grid-connection technical authority service is fixed-scope, and we give conditional endorsement only when the technical conditions are met.

Our review does not replace NSP or AEMO acceptance or guarantee release dates. Independent BESS hold point testing reviews can help improve evidence quality and reduce follow-up requests. If your evidence pack is the bigger worry, our article on BESS energisation delays caused by incomplete compliance evidence shows how to build one.

Book a Technical Triage Before Your Next Hold Point

Tell us where your project sits, which hold points are still ahead and what BESS hold point testing evidence you have so far. We will say whether independent review is a fit for your project. Book a technical triage through our contact page and we will take it from there.